Violation Detail
Standard Cited: 19100119 L01 Process safety management of highly hazardous chemicals.
Inspection Nr: 1411622.015
Citation: 01010
Citation Type: Serious
Abatement Status: Not Completed - Employer Out of Business
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 12/19/2019
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 02/07/2020
Gravity: 10
Report ID: 0317000
Contest Date: 01/06/2020
Final Order: 01/04/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/04/2021 | $13,260.00 | 02/07/2020 | Serious | |
| Penalty | C: Contested | 01/14/2020 | $13,260.00 | 02/07/2020 | Serious | |
| Penalty | Z: Issued | 12/19/2019 | $13,260.00 | 02/07/2020 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.119(l)(1): The employer did not establish or implement written procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process. a) Philadelphia Energy Solutions Refinery Complex, 3144 Passyunk Ave, Philadelphia, PA 19145 - HF Alkylation Unit 433: Employees worked on and in the vicinity of equipment containing highly hazardous chemicals where the employer did not establish and implement written procedures for changing feed composition which contributed to the Deethanizer Charge Pump (P-5A) fire, exposing employees to fire, explosion, toxics, and corrosive hazards, which occurred on and at points up to the destructive event on 6/21/2019. b) Philadelphia Energy Solutions Refinery Complex, 3144 Passyunk Ave, Philadelphia, PA 19145 - HF Alkylation Unit 433: Employees worked on and in the vicinity of equipment containing highly hazardous chemicals where the employer did not establish and implement written procedures for changing V-1s high and high-high pressure control alarm set points which contributed to the Deethanizer Charge Pump (P-5A) fire, exposing employees to fire, explosion, toxics, and corrosive hazards, which occurred on and at points up to the destructive event on 6/21/2019.
Translate