Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 1082421.015
Citation: 01010
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,900.00
Current Penalty: $3,000.00
Issuance Date: 02/04/2016
Nr Instances: 6
Nr Exposed: 45
Abatement Date: 06/30/2016
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 02/25/2016
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/25/2016 | $3,000.00 | 06/30/2016 | Serious | |
| Penalty | Z: Issued | 02/04/2016 | $4,900.00 | 03/18/2016 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going integrity of process equipment: a) Establishment - PEEB Process The employer did not establish and implement written procedures for internal and external inspection of tank WT-100. Violation occurred on or about 8/4/15. b) Establishment - PEEB Process The employer did not establish and implement written procedures for internal and external inspection of autoclave A1. Violation occurred on or about 8/4/15. c) Establishment - PEEB Process The employer did not establish and implement a written procedure for external inspection of process piping. Violation occurred on or about 8/4/15. d) Establishment - PEEB Process The employer did not establish a written procedure for testing grounding of tanks and equipment. Violation occurred on or about 8/4/15. e) Establishment - PEEB Process The employer did not establish and implement a written procedure for inspection of pressure relief valves upon removal. Violation occurred on or about 8/4/15. f) Establishment - PEEB Process The employer did not implement procedure Mech-SOP-003 and Mech-SOP-004 which specify locking isolation valve 153-HV-002 on ethyl chloride tank T-153 and isolation valve WT-HV-SV on weight tank WT-100 open when vessels T-153 & WT-100 are in-service. Violation occurred on or about 8/4/2015.