Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1044850.015
Citation: 01010
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,300.00
Current Penalty: $1,650.00
Issuance Date: 09/02/2015
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 09/25/2015
Gravity: 1
Report ID: 0729700
Contest Date:
Final Order: 09/22/2015
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/22/2015 | $1,650.00 | 09/25/2015 | Serious | |
| Penalty | Z: Issued | 09/02/2015 | $3,300.00 | 09/25/2015 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.147(c)(6)(ii): The employer did not certify that periodic inspections of the energy control procedures had been performed: Employees perform servicing and maintenance activities on equipment including, but not limited to the AU Unit (LO/TO-94-CS1); the Vessel (LO/TO-P004); the Vessel (LO/TO-94-V-1); and the Pump (LO/TO-AP-1) were exposed to hazards associated with the unexpected energizing or start-up of equipment in that periodic inspections of energy control procedures for equipment were not performed nor documented. 29 CFR 1903.19(c)(1) requires certification that the abatement of the above violation is complete.