Violation Detail
Standard Cited: 19261211 C02
Inspection Nr: 1102251.015
Citation: 01009D
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/11/2016
Nr Instances: 3
Nr Exposed: 3
Abatement Date: 08/08/2016
Gravity: 10
Report ID: 0524500
Contest Date: 04/28/2016
Final Order: 10/13/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/13/2016 | $0.00 | 08/08/2016 | Serious | |
Penalty | C: Contested | 05/02/2016 | $0.00 | 05/05/2016 | Serious | |
Penalty | Z: Issued | 04/11/2016 | $0.00 | 05/05/2016 | Serious |
Text For Citation: 01 Item/Group: 009D Hazard:
29 CFR 1926.1211(c)(2): The employer did not ensure that each authorized entrant had the other end of their retrieval line attached to a mechanical device or fixed point outside the permit space in such a manner that rescue can begin as soon as the rescuer becomes aware that rescue is necessary: On or about October 16, 19 and 20, 2015, employees entered confined spaces between the secondary clarifier diversion structure, post aeration building and the diversion structure and the employer did not ensure each entrant had a retrieval line attached to a mechanical device or fixed point outside the space to ensure rescue could begin as soon as necessary.