Violation Detail
Standard Cited: 19100119 J05 Process safety management of highly hazardous chemicals.
Inspection Nr: 313419145
Citation: 01009B
Citation Type: Serious
Abatement Status: X
Initial Penalty:
Current Penalty:
Issuance Date: 11/17/2010
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 04/15/2011
Gravity: 10
Report ID: 0830500
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | 04/04/2011 | 04/15/2011 | Serious | ||
| Penalty | I: Informal Settlement | 11/30/2010 | 01/14/2011 | Serious | ||
| Penalty | Z: Issued | 11/17/2010 | 12/20/2010 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard: CHEMNEP
29 CFR 1910.119(j)(5): The employer did not correct deficiencies in equipment that were outside acceptable limits before further use or in a safe and timely manner: (a)Styro-Tech LLC at 5005 Lima St., Denver, CO 80239: On and before May 18, 2010 the employer did not correct deficiencies in equipment associated with the safe use of isopentane in that the pressure gauge on the isopentane supply tank was broken as evidenced by the needle reading less than zero. Abatement Note: Abatement certification and documentation are required for this item (see enclosed "Sample Abatement Certification Letter").
Translate