Violation Detail
Standard Cited: 19100305 G01 IV B Wiring methods, components, and equipment for general use.
Inspection Nr: 1782385.015
Citation: 01009B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/04/2025
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 05/30/2025
Gravity: 5
Report ID: 0418300
Contest Date:
Final Order: 04/28/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/28/2025 | $0.00 | 05/30/2025 | Serious | |
Penalty | Z: Issued | 04/04/2025 | $0.00 | 04/23/2025 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard:
29 CFR 1910.305(g)(1)(iv)(B): Flexible cords and cables were run through holes in walls, ceilings, or floors: (a) On or about October 17, 2024 - Facility, Abrasive blasting area, a flexible cord was used through a hole in the wall of the blasting booth to provide power to the lights for the interior of the blasting booth.