Violation Detail
Standard Cited: 19260062 E01 Lead
Inspection Nr: 1719988.015
Citation: 01009B
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/05/2024
Nr Instances: 1
Nr Exposed: 34
Abatement Date: 11/04/2024
Gravity: 10
Report ID: 0215000
Contest Date: 07/26/2024
Final Order: 11/18/2024
Related Event Code (REC): R
Emphasis:
Substance: 1591
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/18/2024 | $0.00 | 11/04/2024 | Serious | |
Penalty | C: Contested | 10/24/2024 | $0.00 | 08/21/2024 | Serious | |
Penalty | Z: Issued | 07/05/2024 | $0.00 | 08/21/2024 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard:
29 CFR 1926.62(e)(1):The employer did not implement all feasible engineering and work practice controls, including administrative controls, to reduce and maintain employee exposure to lead to or below the permissible exposure limit: (a) AHERN Painting Contractors (Broadway Junction Train Station J Train Line Project), located at 1549 Herkimer Street, Brooklyn, NY 11207 Employees working on the metal train station columns and conducting the lead-based paint removal via abrasive blasting using steel shot media are exposed to the hazards of chemicals such as, but not limited to, lead. Personal air sampling results revealed that employees are exposed to lead at an 8-hour time-weighted average (TWA) concentration of 53,350 micrograms per cubic meter (ug/m3), approximately 111.15 times the adjusted permissible exposure limit of approximately 39 micrograms per cubic meter of air, during blasting operations based on a 10.27-hour workday. The employer did not ensure that the engineering controls were sufficient to maintain employee exposure to lead to or below the permissible exposure limit. Condition observed on or about February 7, 2024