Violation Detail
Standard Cited: 19100305 G01 IV D Wiring methods, components, and equipment for general use.
Inspection Nr: 1566871.015
Citation: 01009B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/02/2022
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 01/03/2023
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 06/21/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/21/2022 | $0.00 | 01/03/2023 | Serious | |
Penalty | Z: Issued | 06/02/2022 | $0.00 | 06/14/2022 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard:
29 CFR 1910.305(g)(1)(iv)(D):Flexible cords and cables not specifically permitted otherwise in paragraph (g)(1)(ii) of this section, were used where attached to building surfaces: a. Building 1, wrapper area - On or about February 22, 2022, the employer had run a flexible cord from wrapper 3, up to the structural steel trusses affixed it to the trusses and ran over to above Wrapper 1, exposing employees to an electrical hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.