Standard Cited: 19100303 G02 I General.
Inspection Nr: 1159851.015
Citation: 01009B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $0.00
Issuance Date: 12/15/2016
Nr Instances: 3
Nr Exposed: 5
Abatement Date: 01/12/2017
Gravity: 10
Report ID: 0418100
Contest Date: 01/09/2017
Final Order: 10/18/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/18/2017 | $0.00 | 01/12/2017 | Serious | |
Penalty | C: Contested | 01/18/2017 | $12,471.00 | 01/12/2017 | Serious | |
Penalty | Z: Issued | 12/15/2016 | $12,471.00 | 01/12/2017 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard:
29 CFR 1910.303(g)(2)(i): Except as elsewhere required or permitted by Subpart S of Part 1910, live parts of electric equipment operating at 50 volts or more were not guarded against accidental contact by use of approved cabinets or other forms of approved enclosures or by any of the means identified in paragraphs (A), (B), (C), and (D) of 29 CFR 1910.303(g)(2)(i). On 7/19/16, in the Picking Power Room at the Athens facility, employees were exposed to 480 volt electrical hazards as employees, both sanitation and maintenance, routinely accessed electrical panels to turn breakers off for other equipment within the panel that was to be serviced and maintained.