Violation Detail
Standard Cited: 19100334 A02 II Use of equipment.
Inspection Nr: 1049799.015
Citation: 01009B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/22/2015
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 10/14/2015
Gravity:
Report ID: 0627700
Contest Date: 10/12/2015
Final Order: 04/28/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/28/2016 | $0.00 | 10/14/2015 | Other | |
Penalty | C: Contested | 02/29/2016 | $0.00 | 10/14/2015 | Serious | |
Penalty | Z: Issued | 09/22/2015 | $0.00 | 10/14/2015 | Serious |
Text For Citation: 01 Item/Group: 009B Hazard:
29 CFR 1910.334(a)(2)(ii): There was a defect or evidence of damage that could have exposed an employee to injury and the defective or damaged item was not removed from service and an employee was using it before repairs and tests necessary to render the equipment safe were made: On or about March 23, 2015, feed mill, 4th floor, an extension cord used to power drop lights in mash feed bins 84 and 85 had a cut in the outer jacket. Pursuant to 29 C.F.R. 1903.19, within ten (10) days of the abatement date, the employer must submit documentation showing that it is in compliance with the standard, including describing the steps that it is taking to ensure that all damaged electrical equipment is removed from service.