Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 1241239.015
Citation: 01009A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $4,889.00
Current Penalty: $2,444.50
Issuance Date: 08/25/2017
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 1
Report ID: 0215800
Contest Date:
Final Order: 09/19/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/19/2017 | $2,444.50 | Serious | ||
Penalty | Z: Issued | 08/25/2017 | $4,889.00 | Serious |
Text For Citation: 01 Item/Group: 009A Hazard:
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective: a) CNC Dept., on or about 6/29/17: County Line floor fan at the Koch machine was not grounded in that the ground pin was missing from the plug end. b) CNC Dept., on or about 6/29/17: County Line floor fan near the overhead door was not grounded in that the ground pin was missing from the plug end.