Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 980337.015
Citation: 01009
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,800.00
Current Penalty: $1,820.00
Issuance Date: 11/28/2014
Nr Instances: 3
Nr Exposed: 3
Abatement Date: 03/31/2015
Gravity: 10
Report ID: 0418100
Contest Date:
Final Order: 01/30/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/30/2015 | $1,820.00 | 03/31/2015 | Serious | |
Penalty | Z: Issued | 11/28/2014 | $2,800.00 | 12/24/2014 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident. On or about June 10, 2014 at 120 McArthur Road, Marble Hill, GA: Where employees had to access the various electrical panels in the facility, the breakers were not labeled. Employees were exposed to an unexpected energization or de-energization of various pieces of equipment that could result in electrical shock or amputation.