Violation Detail
Standard Cited: 19100430 B04 Equipment.
Inspection Nr: 926866.015
Citation: 01009
Citation Type: Serious
Abatement Date: 02/14/2014 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 02/04/2014
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0418800
Contest Date: 02/27/2014
Final Order: 10/21/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 10/21/2014 | $7,000.00 | 02/14/2014 | Serious | |
Penalty | C: Contested | 03/03/2014 | $7,000.00 | 02/14/2014 | Serious | |
Penalty | Z: Issued | 02/04/2014 | $7,000.00 | 02/14/2014 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.430(b)(4): The output of the air compressor system(s) was not tested for air purity every six months by means of samples taken at the connection to the distribution system, (is applicable to the construction standard by 29 CFR 1926.1090 that incorporates the General Industry requirement): a. On August 6th, 2013, at the above addressed dive site, the employer had not tested the air purity of breathing air supplied to divers by a R260-4 Hookah dive compressor. The dive compressor was purchased and put into use January 2013.