Violation Detail
Standard Cited: 19100305 A02 I Wiring methods, components, and equipment for general use.
Inspection Nr: 311418057
Citation: 01009
Citation Type: Other
Abatement Status: I
Initial Penalty: $1,875.00
Current Penalty: $1,875.00
Issuance Date: 05/15/2009
Nr Instances: 1
Nr Exposed: 14
Abatement Date: 05/20/2009
Gravity: 03
Report ID: 0419400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/08/2009 | $1,875.00 | 05/20/2009 | Other | |
| Penalty | Z: Issued | 05/15/2009 | $1,875.00 | 05/20/2009 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard: REFINERY
29 CFR 1910.305(a)(2)(i) Temporary electrical power and lighting installations 600 volts, nominal, or less was used for purposes other than allowed in 29 CFR 1910.305 (a)(2)(i) sections (A) through (C): (a)Portable building located at the south end of Plant # 81 - On or about February 10, 2009 had temporary wiring that was not removed immediately upon completion of the project.