Violation Detail
Standard Cited: 19100146 K03 Permit-required confined spaces
Inspection Nr: 1438680.015
Citation: 01009
Citation Type: Serious
Abatement Date: 08/02/2021 2
Initial Penalty: $12,145.00
Current Penalty: $7,937.62
Issuance Date: 04/01/2020
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0524200
Contest Date: 04/22/2020
Final Order: 07/06/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/06/2021 | $7,937.62 | 08/02/2021 | Serious | |
Penalty | C: Contested | 04/29/2020 | $12,145.00 | 04/29/2020 | Serious | |
Penalty | Z: Issued | 04/01/2020 | $12,145.00 | 04/29/2020 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.146(k)(3): To facilitate non-entry rescue, retrieval systems or methods were not used whenever an authorized entrant entered a permit space: (a) On October 10, 2019, Hill Mechanical Corp. did not utilize a non-entry rescue retrieval system at steam vault 13 on Northwestern University's Evanston Campus prior to an entry by a Hill Mechanical Corp. employee for the observation of a steam leak. (b) On October 10, 2019, Hill Mechanical Corp. did not utilize a non-entry rescue retrieval system at steam vault 14 on Northwestern University's Evanston Campus prior to an entry by Hill Mechanical Corp. employees for the performance of repairs on the steam system. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.