Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1352866.015
Citation: 01009
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,282.00
Current Penalty: $6,033.00
Issuance Date: 02/13/2019
Nr Instances: 4
Nr Exposed: 8
Abatement Date: 05/31/2019
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 03/12/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/12/2019 | $6,033.00 | 05/31/2019 | Serious | |
Penalty | Z: Issued | 02/13/2019 | $9,282.00 | 04/02/2019 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy. On or about 10/10/18, at the LCY Elastomers facility located in Baytown Texas, the energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy, for equipment including but not limited to the following: a. DAF Effluent Sum Pump P-7689A (P&ID EF-631 Rev. 8) b. Lift Station Pump P -7685A (P&ID EF-631 Rev. 8) c. Air Compressor C-7651A/B (P&ID EF-609 Rev. 8) d. Heat Exchanger (Dry solvent charge Pre-heater) E-7301 (P&ID EF-303 Rev.17)