Violation Detail
Standard Cited: 19100303 G02 I General.
Inspection Nr: 1295906.015
Citation: 01009
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,959.00
Current Penalty: $7,500.00
Issuance Date: 07/26/2018
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 08/21/2018
Gravity: 10
Report ID: 1032500
Contest Date:
Final Order: 08/23/2018
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/23/2018 | $7,500.00 | 08/21/2018 | Serious | |
Penalty | Z: Issued | 07/26/2018 | $9,959.00 | 08/21/2018 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.303(g)(2)(i): Except as elsewhere required or permitted by Subpart S of Part 1910, live parts of electric equipment operating at 50 volts or more were not guarded against accidental contact by use of approved cabinets or other forms of approved enclosures or by any of the means identified in paragraphs (A), (B), (C), and (D) of 29 CFR 1910.303(g)(2)(i): (a) Circuit Breaker Panel - Structural Line 'B' MCC; on February 13, 2018, employees walking or working in the area were exposed to live parts rated at 480V when the door to B24 was left open. (b) Circuit Breaker Panel - Structural Line 'B' MCC; on February 13, 2018, employees walking or working in the area were exposed to live parts rated at 480V when the door to B41 was left open. NOTE: Abatement certification AND documentation are required for this item.