Violation Detail
Standard Cited: 19261101 K02 I Asbestos
Inspection Nr: 1284088.015
Citation: 01009
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,315.00
Current Penalty: $6,236.25
Issuance Date: 04/20/2018
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 05/07/2018
Gravity: 5
Report ID: 0213600
Contest Date:
Final Order: 05/14/2018
Related Event Code (REC): C
Emphasis:
Substance: 9020
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/14/2018 | $6,236.25 | 05/07/2018 | Serious | |
Penalty | Z: Issued | 04/20/2018 | $8,315.00 | 05/07/2018 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1926.1101(k)(2)(i): Before work subject to this standard began, the building and/or facility owner(s) did not determine the presence, location and quantity of asbestos containing material (ACM) and/or presumed asbestos containing material (PACM) at the worksite pursuant to 29 CFR 1926.1101(k)(1): a) Refrigerated Warehouse Area - On or about 10/20/17, the employer did not conduct a comprehensive survey, and did not notify employees who worked in the building of the presence, location, and quantity of ACM and/or PACM within the area prior to the initiation of the removal activity (a Class II activity). During the removal activity, employees knocked down and demolished asbestos containing wallboard which was found to contain 11% chrysotile asbestos. ABATEMENT CERTIFICATION REQUIRED