Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
Inspection Nr: 1113807.015
Citation: 01009
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,410.00
Current Penalty: $4,410.00
Issuance Date: 06/17/2016
Nr Instances: 9
Nr Exposed: 33
Abatement Date: 12/31/2017
Gravity: 10
Report ID: 0522500
Contest Date: 07/07/2016
Final Order: 01/17/2018
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/17/2018 | $4,410.00 | 12/31/2017 | Serious | |
Penalty | C: Contested | 07/11/2016 | $4,410.00 | 07/22/2016 | Serious | |
Penalty | Z: Issued | 06/17/2016 | $4,410.00 | 07/22/2016 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.119(d)(3)(ii): The employer shall document that equipment complies with recognized and generally accepted good engineering practices (RAGAGEP): a. The employer failed to document that the steam coil for the TK 0401-00 Melt Tank was built and installed per RAGAGEP, thereby exposing employees to fire and explosion hazards. b. The employer did not install the relief vent piping on the TK 0712-00 Wash Liquor Storage Tank in accordance with RAGAGEP, as it does not relieve to a safe location, thereby exposing employees to fire and explosion hazards. c. The employer did not install the relief vent piping for the TK 0406-00 Stripped FAME Solvent Receiver in accordance with RAGAGEP, as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards. d. The employer did not install the relief vent piping for the F 0302-00 South RDF in accordance with RAGAGEP, as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards. e. The employer did not install the relief vent piping for the TK 0401-00 Melt Tank in accordance with RAGAGEP, as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards. f. The employer did not install the F 0302-00 South RDF LEL meter in accordance with RAGAGEP, as it was not sealed to prevent vapor penetration, thereby exposing employees to fire and explosion hazards. g. The employer did not install the relief vent piping for the TK 0405-00 FAME Recovery Tank in accordance with RAGAGEP, as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards. h. The employer did not install the relief vent piping for the TK 0202-00 Crystallization (XTAL) Slurry Storage Tank in accordance with RAGAGEP, as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards. i. The employer did not install the relief vent piping for TK0502-00 Evaporator in accordance with RAGAGEP as it did not relieve to a safe location, thereby exposing employees to fire and explosion hazards.