Violation Detail
Standard Cited: 19100303 G01 General.
Inspection Nr: 1588581.015
Citation: 01008A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,256.00
Current Penalty: $7,600.00
Issuance Date: 09/28/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 10/11/2022
Gravity: 5
Report ID: 0627700
Contest Date:
Final Order: 11/04/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/04/2022 | $7,600.00 | 10/11/2022 | Serious | |
Penalty | Z: Issued | 09/28/2022 | $10,256.00 | 10/11/2022 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1910.303(g)(1):Sufficient access and working space was not provided and maintained about all electric equipment (operating at 600 volts, nominal, or less to ground) to permit ready and safe operation and maintenance of such equipment: On or about July 28 2022 employees accessing panels were exposed to electric shock hazards in the following instances: a) The circuit breaker controlling the compressor next to the spiral steps to the second-floor storage area is blocked by pallets. b) The circuit breakers that belong to TF 1 and TF 2 are blocked by a table. c) The circuit breaker box handle was blocked by Machine Press MP9. Instance C Removed?