Violation Detail
Standard Cited: 19100025 B06 Stairways.
Inspection Nr: 1207843.015
Citation: 01008A
Citation Type: Serious
Abatement Date: 04/03/2018 2
Initial Penalty: $3,802.00
Current Penalty: $1,825.00
Issuance Date: 06/26/2017
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 1
Report ID: 0215800
Contest Date: 07/09/2017
Final Order: 02/02/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/02/2018 | $1,825.00 | 04/03/2018 | Serious | |
Penalty | C: Contested | 07/26/2017 | $3,802.00 | 07/07/2017 | Serious | |
Penalty | Z: Issued | 06/26/2017 | $3,802.00 | 07/07/2017 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1910.25(b)(6): Each stair could not support at least five times the normal anticipated live load, but never less than a concentrated load of 1,000 pounds (454 kg) applied at any point; a) On or about 2/7/2017, Outside: Steps leading to the diesel tank were damaged with failed welds. Abatement certification is required for these items.