Violation Detail
Standard Cited: 19100212 A General requirements for all machines.
Inspection Nr: 1185446.015
Citation: 01008A
Citation Type: Serious
Abatement Date: 03/09/2017 2
Initial Penalty: $8,873.00
Current Penalty: $2,500.00
Issuance Date: 02/02/2017
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC): C
Gravity: 10
Report ID: 0317900
Contest Date: 03/02/2017
Final Order: 03/12/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/12/2018 | $2,500.00 | 03/09/2017 | Serious | |
Penalty | C: Contested | 03/06/2017 | $8,873.00 | 03/09/2017 | Serious | |
Penalty | Z: Issued | 02/02/2017 | $8,873.00 | 03/09/2017 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1910.212(a): One or more methods of machine guarding were not provided to protect the operator and other employees in the machine area from hazards such as those created by ingoing nip points at the point of operation: a) SS Industries - On or about November 1, 2016, an employees operating a power driven pipe bender was exposed to amputation hazards created by ingoing nip points where the power drive and guide rollers meet the metal pipe. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photograph or video evidence of abatement or other written records.