Violation Detail
Standard Cited: 19261101 G05 V Asbestos
Inspection Nr: 1141444.015
Citation: 01008A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,988.00
Current Penalty: $2,400.00
Issuance Date: 10/18/2016
Nr Instances: 5
Nr Exposed: 5
Abatement Date: 11/16/2016
Gravity: 10
Report ID: 0523300
Contest Date: 11/07/2016
Final Order: 07/30/2018
Related Event Code (REC):
Emphasis:
Substance: 9020
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/30/2018 | $2,400.00 | 11/16/2016 | Serious | |
Penalty | C: Contested | 11/09/2016 | $4,988.00 | 11/16/2016 | Serious | |
Penalty | Z: Issued | 10/18/2016 | $4,988.00 | 11/16/2016 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1926.1101(g)(5)(v): Water Spray Process System. A water spray process system may be used for removal of ACM and PACM from cold line piping if, employees carrying out such process have completed a 40-hour separate training course in its use, in addition to training required for employees performing Class I work. On or about April 20, 2016 employees were using a water spray system when performing class I work without an additional 40 hour training course.