Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1135019.015
Citation: 01008A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,800.00
Current Penalty: $7,000.00
Issuance Date: 07/20/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/01/2016
Gravity: 10
Report ID: 0215000
Contest Date: 08/19/2016
Final Order: 12/27/2016
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/27/2016 | $7,000.00 | 08/01/2016 | Serious | |
| Penalty | C: Contested | 08/19/2016 | $2,800.00 | 08/01/2016 | Serious | |
| Penalty | Z: Issued | 07/20/2016 | $2,800.00 | 08/01/2016 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) Location: 1604 Broadway second floor On or about: 25 March 2016 a) Employees worked on a mobile tubular welded frame scaffold that was not fully planked or decked.