Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 554380.015
Citation: 01008
Citation Type: Serious
Abatement Date: 10/17/2012 2
Initial Penalty: $3,400.00
Current Penalty: $2,040.00
Issuance Date: 09/25/2012
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0419400
Contest Date:
Final Order: 10/23/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/23/2012 | $2,040.00 | 10/17/2012 | Serious | |
Penalty | Z: Issued | 09/25/2012 | $3,400.00 | 10/17/2012 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: a) In the GAD production storage - On or about July 25, 2012, The circuit breaker panels were not labeled. b) In the GAD production room - On or about July 25, 2012, The circuit breaker panel by the long yellow catwalk soap deck was not labeled.