Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.

Inspection Nr: 314054685

Citation: 01008

Citation Type: Serious

Abatement Status: X

Initial Penalty: $1,250.00

Current Penalty:

Issuance Date: 06/25/2010

Nr Instances: 2

Nr Exposed: 10

Abatement Date: 11/30/2010

Gravity: 03

Report ID: 0728900

Contest Date:

Final Order:

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 07/13/2010 11/30/2010 Serious  
Penalty Z: Issued 06/25/2010 $1,250.00 08/27/2010 Serious  

Text For Citation: 01 Item/Group: 008 Hazard: CHEMNEP

29 CFR 1910.119(j)(2): Equalizer Midwest, Inc. - Hastings, NE - The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment. Facility mechanical integrity program did not establish and implement written procedures to address repair, replacement and/or testing of process equipment including, but not limited to pressure relief valves, pressure vessels and piping. Abatement certification is required for this violation. The abatement certification sheet is enclosed with the citations.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.