Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 313797292
Citation: 01008
Citation Type: Serious
Abatement Status: X
Initial Penalty: $4,200.00
Current Penalty: $2,500.00
Issuance Date: 08/19/2010
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 11/01/2010
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/10/2010 | $2,500.00 | 11/01/2010 | Serious | |
| Penalty | Z: Issued | 08/19/2010 | $4,200.00 | 10/05/2010 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard: CHEMNEP
29 CFR 1910.119(j)(4)(i): Inspections and tests were not performed on process equipment to maintain its mechanical integrity: Facility: The employer did not conduct inspections and tests on the process equipment such as, but not limited to: 1)Skid mounted system containing recycle pumps, tanks, piping, instrumentation controls 2) Remote Mounted Motor Control Center 3)Marley Cooling Tower and associated motors, pumps, tanks, and level control 4)30 SCFM 10 HP chlorine tank care padding unit 5)Provent Chlorine Scrubber 6)Chlorine tank car unloading system 7)Unipro shutoff system equipment 8)Pressure relief valves 9)Chlorine gas detectors The inspections and tests shall comply with the provisions of 29 CFR 1910.119(j)(4)(ii), (iii), and (iv).,