Violation Detail
Standard Cited: 19100305 B01 II Wiring methods, components, and equipment for general use.
Inspection Nr: 1705601.015
Citation: 01008
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $2,765.00
Current Penalty: $2,000.00
Issuance Date: 03/18/2024
Nr Instances: 2
Nr Exposed: 14
Abatement Date: 10/16/2024
Gravity: 1
Report ID: 0316700
Contest Date:
Final Order: 04/25/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/25/2024 | $2,000.00 | 10/16/2024 | Serious | |
Penalty | Z: Issued | 03/18/2024 | $2,765.00 | 04/11/2024 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed: a) Cabinet Room - A knockout plug was missing on an outlet between the General table saw (Model 350) and Grizzly dust collector exposing employees to combustible dust explosion hazards and electrical shock, on or about October 23, 2023. b) Sanding Room - The face plate on a 20amp outlet/toggle switch, behind the Bridgewood BW-3S wood shaper, was not effectively closed in that the toggle switch opening was taped over exposing employees to combustible dust explosion hazards and electrical shock, on or about October 23, 2023. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.