Violation Detail
Standard Cited: 19100303 G01 General.
Inspection Nr: 1558666.015
Citation: 01008
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $8,778.00
Current Penalty: $3,511.20
Issuance Date: 12/14/2021
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0729700
Contest Date:
Final Order: 01/19/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/19/2022 | $3,511.20 | Other | ||
Penalty | Z: Issued | 12/14/2021 | $8,778.00 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.303(g)(1):Sufficient access and working space was not provided and maintained about all electric equipment (operating at 600 volts, nominal, or less to ground) to permit ready and safe operation and maintenance of such equipment: In the Laser Cutting Area, employees engaged in production activities were exposed to electrical, and fire hazards in that the service disconnect switches were obstructed by a barrier chain, a vertical fan, and two computer stations.