Violation Detail
Standard Cited: 19261051 A General requirements.
Inspection Nr: 1240638.015
Citation: 01008
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,622.00
Current Penalty: $2,173.00
Issuance Date: 11/08/2017
Nr Instances: 2
Nr Exposed: 2
Abatement Date: 11/17/2017
Gravity: 5
Report ID: 0316400
Contest Date:
Final Order: 11/28/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/28/2017 | $2,173.00 | 11/17/2017 | Serious | |
Penalty | Z: Issued | 11/08/2017 | $3,622.00 | 11/17/2017 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1926.1051(a): Stairways or ladders were not provided at all personnel points of access where there was a break in elevation of 19 inches (48 cm) or more, and no ramp, runway, sloped embankment, or personnel hoist was provided. (a) Tabor Machine Company, Upper Building: On or about June 16, 2017, and times prior, employees were climbing up to 45 inches, from the Biljax frame scaffold working level, to and from the lower end of the connected steel of the upper building structure, up to 13ft. 4in. above grade. (b) Tabor Machine Company, Upper Building: On or about June 16, 2017, and times prior, employees climbed approximately 37 inches from the roof of a building up to the roof of the adjacent building to perform roofing work, up to 15ft. 7in. above grade.