Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 1164052.015
Citation: 01008
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,483.00
Current Penalty: $3,747.00
Issuance Date: 10/28/2016
Nr Instances: 1
Nr Exposed: 21
Abatement Date: 11/07/2017
Gravity: 5
Report ID: 0213100
Contest Date: 11/09/2016
Final Order: 10/23/2017
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/23/2017 | $3,747.00 | 11/07/2017 | Serious | |
Penalty | C: Contested | 11/30/2016 | $7,483.00 | 11/09/2016 | Serious | |
Penalty | Z: Issued | 10/28/2016 | $7,483.00 | 11/09/2016 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective: a) Mill building - On July 26, 2016, or at times prior the power cord for the Rigid Drill Press did not have a ground prong, or other connection to ground.