Standard Cited: 19100119 L01 Process safety management of highly hazardous chemicals.
Inspection Nr: 1151337.015
Citation: 01008
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $12,471.00
Issuance Date: 11/15/2016
Nr Instances: 5
Nr Exposed: 50
Abatement Date: 05/25/2019
Gravity:
Report ID: 0214200
Contest Date: 12/08/2016
Final Order: 03/05/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/05/2018 | $12,471.00 | 05/25/2019 | Other | |
Penalty | C: Contested | 12/13/2016 | $12,471.00 | 12/29/2016 | Serious | |
Penalty | Z: Issued | 11/15/2016 | $12,471.00 | 12/29/2016 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.119(l)(1): The employer did not implement procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process: a) Butanization Process Management of change procedures were not implemented when the procedure "Work Instruction #50-010-Wi5" was changed to include how to check for butane leaks in 2015. b) Butanization Process Management of change procedures were not implemented when the procedure "Work Instruction #50-010-Wi5" was changed to include how to check the R/C sump and butane line bleed valve in 2015. c) Butanization Process Management of change procedures were not implemented when an audible/visual alarm at 25% LEL setpoint at road entrance to unloading area was implemented in 2015. d) Butanization Process Management of change procedures were not implemented when an alarm at 40% LEL to activate shutdown/deluge was implemented in 2015. e) Butanization Process Management of change procedures were not implemented when INPR-9-01 & NPRR-9-01 bypass valves were car sealed closed in 2015. Violation occurred on or about 5/17/2016.