Violation Detail
Standard Cited: 19100217 C03 III F Mechanical power presses.
Inspection Nr: 1071380.015
Citation: 01008
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,900.00
Current Penalty: $2,940.00
Issuance Date: 11/18/2015
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 12/03/2015
Gravity: 10
Report ID: 0522300
Contest Date:
Final Order: 12/03/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/03/2015 | $2,940.00 | 12/03/2015 | Serious | |
| Penalty | Z: Issued | 11/18/2015 | $4,900.00 | 12/03/2015 | Serious |
Text For Citation: 01 Item/Group: 008 Hazard:
29 CFR 1910.217(c)(3)(iii)(f): Mechanical power press(es) using presence sensing point of operation devices were not provided with guards to protect all areas of entry to the point of operation not protected by the presence sensing device; On or about June 17, 2015, the employer failed to ensure that the presence sensing point of operation devices on press #110 were provided with guards to protect the blanked areas. Sections of the light curtain present were blanked by paper and taped to the equipment. These areas were not guarded to prevent employee exposure to the point of operation.