Violation Detail
Standard Cited: 19100119 F01 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 1269114.015
Citation: 01007J
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/06/2018
Nr Instances: 2
Nr Exposed: 7
Abatement Date: 11/30/2018
Gravity: 5
Report ID: 0213900
Contest Date:
Final Order: 04/30/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | 11/07/2018 | $0.00 | 11/30/2018 | Serious | |
Penalty | P: Petition to Mod Abatement | 09/13/2018 | $0.00 | 10/30/2018 | Serious | |
Penalty | P: Petition to Mod Abatement | 06/28/2018 | $0.00 | 08/30/2018 | Serious | |
Penalty | I: Informal Settlement | 04/30/2018 | $0.00 | 06/29/2018 | Serious | |
Penalty | Z: Issued | 04/06/2018 | $0.00 | 05/02/2018 | Serious |
Text For Citation: 01 Item/Group: 007J Hazard:
29 CR 1910.119(f)(1)(iv) The employer did not develop and implement written operating procedures that provided clear instructions for safely conducting activities involved in each covered process consistent with the process safety information that addressed safety systems and their functions: a) GEA/FES ammonia refrigeration system: The SOP OPS-10A for LK 18 and LK19 spiral air units, did not discuss the safety systems, such as, but not limited to, temperature and pressure alarms and the hot gas interlocks, on or about 10/10/17. b) Frick ammonia refrigeration system: The SOPs RESOP 17-20 SP1 C1-4 Spiral Freezer Coils, did not discuss the safety systems, such as, but not limited to, the hot gas interlocks, on or about 10/10/17. NOTE: THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT CERTIFICATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.