Standard Cited: 19101000 E Air contaminants.

Inspection Nr: 958068.015

Citation: 01007B

Citation Type: Other

Abatement Status: Abatement Completed

Initial Penalty: $0.00

Current Penalty: $0.00

Issuance Date: 07/31/2014

Nr Instances: 1

Nr Exposed: 20

Abatement Date: 02/01/2015

Gravity:

Report ID: 0418100

Contest Date:

Final Order: 08/22/2014

Related Event Code (REC): C

Emphasis:

Substance: 9010


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 08/22/2014 $0.00 02/01/2015 Other  
Penalty Z: Issued 07/31/2014 $0.00 12/15/2014 Serious  

Text For Citation: 01 Item/Group: 007B Hazard:

29 CFR 1910.1000(e): Feasible administrative or engineering controls were not determined and implemented to achieve compliance with the limits prescribed in 29 CFR 1910.1000(a) through (d): Rust-Oleum Corporation, at 715 Park North Boulevard, Clarkston, GA - on or about March 4, 2014, engineering controls were not implemented where an employee was exposed to silica at 0.3543 milligrams per cubic meter as an eight hour time weighted average (8-hour TWA), which was 2.4 times the permissible exposure limit. The employee's exposure was monitored for 475 minutes; the remaining five minutes were assumed to be a zero exposure. Abatement Schedule: Step 1 - A written detailed plan of abatement shall be submitted to the Area Director outlining a schedule for the implementation of engineering and/or administrative measures to control employee exposures to hazardous substances as referenced in this citation. This plan shall include, at a minimum, target dates for the following actions which must be consistent with the abatement dates required by this citation: (1) Evaluation of engineering/administrative control options; (2) Selection of optimum control methods and completion of design; (3) Procurement, installation, and operation of selected control measures; (4) Testing and acceptance or modification/redesign of controls. All proposed control measures shall be approved for each particular use by a competent industrial hygienist or other technically qualified person. Thirty-day progress reports are required during the abatement period. Step 2 - Abatement shall be completed by the implementation of feasible engineering controls and/or administrative controls upon verification of their effectiveness in achieving compliance. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.