Violation Detail
Standard Cited: 19100303 B07 III General.
Inspection Nr: 1655540.015
Citation: 01007B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/08/2023
Nr Instances: 2
Nr Exposed: 5
Abatement Date: 10/06/2023
Gravity: 5
Report ID: 0636900
Contest Date: 09/29/2023
Final Order: 06/28/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/28/2024 | $0.00 | 10/06/2023 | Serious | |
Penalty | C: Contested | 09/29/2023 | $0.00 | 10/06/2023 | Serious | |
Penalty | Z: Issued | 09/08/2023 | $0.00 | 10/06/2023 | Serious |
Text For Citation: 01 Item/Group: 007B Hazard:
29 CFR 1910.303(b)(7)(iii): Internal parts of electrical equipment, including busbars, wiring terminals, insulators, and other surfaces, were damaged or contaminated by foreign materials such as paint, plaster, cleaners, abrasives, or corrosive residues. On or about March 9, 2023, and times prior thereto, internal components of live electrical boxes and cabinets were contaminated by a foreign substance identified as the by-products of the glass recycling process, exposing employees to electric shock, electrocution, and fire hazards, in the following instances (a-b): a) The Main Control Panels in the 12-Mesh Building; and b) Breaker Box in the 5/8 Building along Southern Wall.