Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 448973.015
Citation: 01007A
Citation Type: Serious
Abatement Date: 12/19/2012 2
Initial Penalty: $1,600.00
Current Penalty: $1,500.00
Issuance Date: 11/16/2012
Nr Instances: 6
Nr Exposed: 12
Related Event Code (REC):
Gravity: 5
Report ID: 0728500
Contest Date: 12/10/2012
Final Order: 02/27/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/27/2014 | $1,500.00 | 12/19/2012 | Serious | |
Penalty | C: Contested | 01/17/2013 | $1,600.00 | 12/19/2012 | Serious | |
Penalty | Z: Issued | 11/16/2012 | $1,600.00 | 12/19/2012 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) did not present a smooth edge and end and projected more than one half the diameter of the shaft: (a) The projecting ends of four shafts 1 3/4 inch in diameter projected 2 1/2 inches and were not guarded by a nonrotating caps or sleeves along the roller casing coming from the Brewco Saw; and (b) The projecting ends of two shafts 1 3/4 inch in diameter projected 2 1/2 inches and were not guarded by a nonrotating caps or sleeves along the roller casing coming from the head saw.