Violation Detail
Standard Cited: 19101025 E03 II E Lead.
Inspection Nr: 1738263.015
Citation: 01007A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $9,794.00
Issuance Date: 09/06/2024
Nr Instances: 1
Nr Exposed: 318
Abatement Date: 01/02/2025
Gravity: 10
Report ID: 0729300
Contest Date:
Final Order: 09/27/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/27/2024 | $9,794.00 | 01/02/2025 | Serious | |
Penalty | Z: Issued | 09/06/2024 | $16,131.00 | 10/24/2024 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.1025(e)(3)(ii)(E): A detailed schedule for implementation of the program, including documentation such as copies of purchase orders for equipment, construction contracts, etc.; At 18594 Hwy KK in Boss, MO 65440 (Refinery) - On or about 27 March 2024, employees of The Buick Resource Recycling Facility (BRRF) DBA Doe Run were exposed to lead hazards as there was not a detailed schedule for implementation of the program, including documentation such as copies of purchase orders for equipment, construction contracts, etc.