Violation Detail
Standard Cited: 19100305 E01 Wiring methods, components, and equipment for general use.
Inspection Nr: 1601440.015
Citation: 01007A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,116.00
Current Penalty: $8,000.00
Issuance Date: 11/30/2022
Nr Instances: 1
Nr Exposed: 54
Abatement Date: 01/02/2024
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 12/21/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/21/2022 | $8,000.00 | 01/02/2024 | Serious | |
Penalty | Z: Issued | 11/30/2022 | $9,116.00 | 12/19/2022 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.305(e)(1): Cabinets, cutout boxes, fittings, boxes, and panelboard enclosures in damp or wet locations were not installed to prevent moisture or water from entering and accumulating within the enclosures: (a) 158 West Jackson Street, New Holland PA, EMS Washdown Room - On or about July 19, 2022, the two electrical outlets underneath the disconnect switches on the wall were not maintained for wet locations in that the self-closing covers or protective over shield had been removed or broken off, exposing employees to an electrical hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.