Violation Detail
Standard Cited: 19100119 L01 Process safety management of highly hazardous chemicals.
Inspection Nr: 1516919.015
Citation: 01007A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $13,653.00
Current Penalty: $13,653.00
Issuance Date: 08/26/2021
Nr Instances: 3
Nr Exposed: 15
Abatement Date: 09/30/2021
Gravity: 10
Report ID: 0627100
Contest Date: 09/24/2021
Final Order: 02/22/2022
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/22/2022 | $13,653.00 | 09/30/2021 | Serious | |
Penalty | C: Contested | 09/24/2021 | $13,653.00 | 09/30/2021 | Serious | |
Penalty | Z: Issued | 08/26/2021 | $13,653.00 | 09/30/2021 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.119(l)(1):The employer did not implement procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process: On or about February 27, 2021 and at times prior thereto in at the Lion Oil Refinery in El Dorado, AR the employer did not implement procedures to manage changes to process unit. (a) Piping was added to the process in Unit 6 to allow the Stripper Column to be charged with Naphtha from Unit 9. (b) Piping was added to the process in Unit 9 to allow the Unit 6 Stripper Column to be charged with Naphtha from the Unit 9 process. (c) Process piping was routed in the roadway between Unit 6 and Unit 9.