Violation Detail
Standard Cited: 19260454 A Training requirements.
Inspection Nr: 961406.015
Citation: 01007
Citation Type: Serious
Abatement Date: 10/31/2014 2
Initial Penalty: $2,800.00
Current Penalty: $500.00
Issuance Date: 07/03/2014
Nr Instances: 7
Nr Exposed: 7
Related Event Code (REC):
Gravity: 10
Report ID: 0213900
Contest Date: 07/31/2014
Final Order: 12/01/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 12/01/2014 | $500.00 | 10/31/2014 | Serious | |
Penalty | C: Contested | 08/01/2014 | $2,800.00 | 07/30/2014 | Serious | |
Penalty | Z: Issued | 07/03/2014 | $2,800.00 | 07/30/2014 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards: a) 104 Emerson Court Construction Site - Employees without proper training were working from three improperly setup aluminum pump jack scaffolds, on or about 03/05/14. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM, FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.