Violation Detail
Standard Cited: 19100159 C10 Automatic sprinkler systems.
Inspection Nr: 954623.015
Citation: 01007
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $3,300.00
Current Penalty: $3,300.00
Issuance Date: 07/10/2014
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 07/29/2014
Gravity:
Report ID: 0214200
Contest Date: 07/29/2014
Final Order: 07/23/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 07/23/2015 | $3,300.00 | 07/29/2014 | Other | |
| Penalty | C: Contested | 07/30/2014 | $3,300.00 | 07/29/2014 | Serious | |
| Penalty | Z: Issued | 07/10/2014 | $3,300.00 | 07/29/2014 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.159(c)(10): The minimum vertical clearance of 18 inches between automatic sprinkler systems sprinklers and the material below was not maintained: a. Newark Liberty International Airport, Terminal C, Material Services (Stores), Bulk Stores The minimum vertical clearance of 18 inches between the automatic sprinkler system and the material below was not maintained. Employees stacked boxes of materials on metal shelving systems in a manner which did not allow for 18 inch clearance. Materials were stored approximately 9 inches from sprinkler heads. Violation observed on or about March 12, 2014