Violation Detail
Standard Cited: 19100303 B01 General.
Inspection Nr: 923139.015
Citation: 01007
Citation Type: Serious
Abatement Date: 12/20/2013 2
Initial Penalty: $3,300.00
Current Penalty: $2,550.00
Issuance Date: 10/17/2013
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 1
Report ID: 0418100
Contest Date:
Final Order: 11/13/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/13/2013 | $2,550.00 | 12/20/2013 | Serious | |
Penalty | Z: Issued | 10/17/2013 | $3,300.00 | 10/29/2013 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees: a) Plant, Molding Machine #4, aisle - The power cable for the 44 in. galvanized air circulator was frayed in proximity of the male plug, and was partially covered with electrical tape. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).