Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.

Inspection Nr: 584358.015

Citation: 01007

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $6,000.00

Current Penalty: $2,000.00

Issuance Date: 02/08/2013

Nr Instances: 2

Nr Exposed: 16

Abatement Date: 03/07/2013

Gravity: 5

Report ID: 0419700

Contest Date:

Final Order: 02/22/2013

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 02/22/2013 $2,000.00 03/07/2013 Serious  
Penalty Z: Issued 02/08/2013 $6,000.00 03/07/2013 Serious  

Text For Citation: 01 Item/Group: 007 Hazard:

29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) did not present a smooth edge and end and projected more than one half the diameter of the shaft: a. On or about September 10, 2012, in the bottling area on line 1, shafts protruding from the conveyor system measuring 3-inch in length and 1 inch in diameter were not guarded, exposing employees to a caught in hazard. b. On or about September 10, 2012, on the upper level in the palletizing area, shafts protruding from the conveyor system measuring 2-inch and 5-inch in length and 1 inch in diameter were not guarded, exposing employees to a caught on hazard.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.