Violation Detail
Standard Cited: 19260451 F06 General requirements.
Inspection Nr: 423123.015
Citation: 01007
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $3,500.00
Issuance Date: 10/29/2012
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 10/30/2012
Gravity: 10
Report ID: 0317000
Contest Date:
Final Order: 11/15/2012
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/15/2012 | $3,500.00 | 10/30/2012 | Serious | |
Penalty | Z: Issued | 10/29/2012 | $7,000.00 | 10/30/2012 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1926.451(f)(6): The clearance between scaffolds and power lines shall be as follows: Scaffolds shall not be erected, used, dismantled, altered, or moved such that they or any conductive material handled on them might come closer to exposed and energized power lines. a) Jobsite - 2000 Parrish Street - The clearance between the tubular welded scaffold and the energized power line was less than 10 feet. An employee contacted an energized line while hoisting a bucket of mortar mix on or about 4/30/12.