Violation Detail
Standard Cited: 19100305 B01 II Wiring methods, components, and equipment for general use.
Inspection Nr: 1450674.015
Citation: 01007
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,398.00
Current Penalty: $2,699.00
Issuance Date: 05/19/2020
Nr Instances: 3
Nr Exposed: 25
Abatement Date: 06/22/2020
Gravity: 5
Report ID: 0420600
Contest Date:
Final Order: 06/15/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/15/2020 | $2,699.00 | 06/22/2020 | Serious | |
Penalty | Z: Issued | 05/19/2020 | $5,398.00 | 06/22/2020 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed: a. On or about 12/12/2019, at the fabrication area near the MEP bending machines, employees were exposed to electrical hazards, in that, a 240 volts main power disconnect was missing a panel cover and had 3 breaker openings without a cover. b. On or about 12/12/2019, at the fabrication area near column N-11, employees were exposed to electrical hazards, in that, a 240 volts control panel had an opening of 3 inches by 2 inches without a cover. c. On or about 12/12/2019, at the fabrication area near MEP 91, employees were exposed to electrical hazards, in that, a 240 volt red breaker box had a knockout missing from the side of the box.