Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 1405933.015
Citation: 01007
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,376.00
Current Penalty: $4,376.00
Issuance Date: 10/10/2019
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 10/23/2019
Gravity: 1
Report ID: 0215800
Contest Date: 10/25/2019
Final Order: 05/12/2021
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/12/2021 | $4,376.00 | 10/23/2019 | Serious | |
Penalty | C: Contested | 10/28/2019 | $4,376.00 | 10/23/2019 | Serious | |
Penalty | Z: Issued | 10/10/2019 | $4,376.00 | 10/23/2019 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective: a) On or about 6/7/2019, Production Area: A metal cased "Sweed" scrap chopper was not provided with a continuous path to ground. Abatement certification is required for this item.