Violation Detail
Standard Cited: 19100334 B02 Use of equipment.
Inspection Nr: 1193905.015
Citation: 01007
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $9,959.00
Current Penalty: $9,959.00
Issuance Date: 05/19/2017
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0419700
Contest Date: 06/09/2017
Final Order: 08/29/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/29/2018 | $9,959.00 | Serious | ||
Penalty | C: Contested | 06/13/2017 | $9,959.00 | Serious | ||
Penalty | Z: Issued | 05/19/2017 | $9,959.00 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.334(b)(2): The repetitive manual reclosing of circuit breakers or reenergizing electric power and lighting circuits through replaced fuses was not prohibited: a: On or about November 29, 2016, at the plant, on the first floor of the plant on the northeast side, the employer allowed employees to manually reach inside the programmable logic controller (PLC) attached to the re-spool machine on the take-up side to reset breakers while the machine was energized, exposing employees to electrical shock hazards.