Violation Detail
Standard Cited: 19100333 B02 II A Selection and use of work practices
Inspection Nr: 921056.015
Citation: 01006C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/27/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 10/17/2013
Gravity: 5
Report ID: 0111400
Contest Date:
Final Order: 09/26/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/26/2013 | $0.00 | 10/17/2013 | Serious | |
| Penalty | Z: Issued | 08/27/2013 | $0.00 | 10/17/2013 | Serious |
Text For Citation: 01 Item/Group: 006C Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment were not determined before circuits and equipment were denergized: Pin Setting Station: Safe procedures for deenergizing the electrical chassis boxes were not developed.