Violation Detail
Standard Cited: 19100119 D03 IB Process safety management of highly hazardous chemicals.
Inspection Nr: 312412166
Citation: 01006B
Citation Type: Other
Abatement Date: 04/09/2011 X
Initial Penalty:
Current Penalty: $1,750.00
Issuance Date: 02/25/2010
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 01
Report ID: 0854910
Contest Date: 03/30/2010
Final Order: 03/10/2011
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/10/2011 | $1,750.00 | 04/09/2011 | Other | |
Penalty | Z: Issued | 02/25/2010 | 03/30/2010 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard: REFINERY
29 CFR 1910.119 (d)(3)(i)[B] Information pertaining to the equipment in the process shall include Piping and instrument diagrams (P&ID's): (a) At the time of the inspection, Thursday, October 22, 2009 through Monday, February 22, 2010, of Tesoro Refining and Marketing Co. 474 W. 900 N. Salt Lake City, UT, Compliance Officers reviewed the process safety information (psi) pertaining to the equipment in the process. The psi did not include an up to date and accurate piping and instrument diagram (P&ID). Review of the P&ID D-N2C-34-031 did not include the change in steam pressure of 170 psig feeding Pump 112B (P-112) to approximately 85 psig. During interviews, employees stated the change in steam pressure for the KO drum pump, P-112, was done about a year prior to a south flare stack fire on the night of 10/21/09. By not maintaining accurate and up to date P&ID's, employees were deprived of critical process safety information related to their work area. Serious injury could occur due to being provided with incorrect information.